DOC-03 Plan
Plan
The programme's steps, with timelines, effort, owners and dependencies.
Plan
v0.1 draft | 10 November 2026
Post Automation Utopia programme | Owner: Programme Director
Programme steps by phase. Steps P0-01 to P0-13 are the Next steps (NS-01 to NS-13). Dates and effort are recommendations: indicative, sized relatively and not costed. See the Key tab.
| ID | Step | Phase | Workstream | Description | Start | End | Duration (months) | Effort | Owner (accountable) | Delivered by (responsible) | Depends on | Output | Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P0-01 | Mobilise the programme | Phase 0 | Programme management | Confirm the Sponsor, Programme Board, Programme Director and PMO. Set up the Control register and approve the PID. | Jan 2027 | Mar 2027 | 3 | Medium | Sponsor | Programme Director; PMO Lead | Sponsor, Programme Board and core team in place. PID approved. Control register in use. | Not started | |
| P0-02 | Agree governance and decision rights | Phase 0 | Programme management | Agree terms of reference for the Programme Board and Design Authority, tolerances, escalation routes and the baselined RACI. | Jan 2027 | Mar 2027 | 3 | Small | Programme Director | PMO Lead; Legal and Policy Lead | P0-01 | Terms of reference, tolerances and RACI v1.0. | Not started |
| P0-03 | Map stakeholders and agree the engagement strategy | Phase 0 | Engagement and legitimacy | Map stakeholders worldwide and agree how each will be engaged, including the method for appointing human proxies for animals, plants and ecosystems. | Feb 2027 | May 2027 | 4 | Medium | Engagement and Legitimacy Lead | Civil society and labour organisations; Conservation science bodies | P0-01 | Stakeholder map, engagement strategy and proxy method. | Not started |
| P0-04 | Review the evidence | Phase 0 | Design authority | Review the evidence on automation trends, basic income pilots, universal basic services, housing and ecological limits. | Mar 2027 | Oct 2027 | 8 | Large | Design Authority Lead | Academia and research institutes; Economic Security Lead; Basic Services Lead; Automation and AI Governance Lead; Purpose, Learning and Participation Lead; Planetary Stewardship Lead | P0-01 | Evidence report for each pillar. | Not started |
| P0-05 | Model scenarios and fiscal options | Phase 0 | Economic security | Build slow, central and fast automation scenarios and size the income floor and services options relative to each other. | May 2027 | Jan 2028 | 9 | Large | Economic Security Lead | Academia and research institutes; Central banks; International financial institutions | P0-04 | Automation scenarios and relative fiscal sizing of the options. | Not started |
| P0-06 | Appraise the options for each pillar | Phase 0 | Design authority | Appraise the options for each pillar, including the mix of cash and services, housing delivery models and ownership models for automated capital. | Sep 2027 | Feb 2028 | 6 | Large | Design Authority Lead | Economic Security Lead; Basic Services Lead; Automation and AI Governance Lead; Purpose, Learning and Participation Lead; Planetary Stewardship Lead; Legal and Policy Lead | P0-04, P0-05 | Options report with a recommended option for each pillar. | Not started |
| P0-07 | Consult worldwide | Phase 0 | Engagement and legitimacy | Consult people across regions, sectors and generations, and hold proxy-led hearings for animals, plants and ecosystems. | Sep 2027 | Mar 2028 | 7 | Very large | Engagement and Legitimacy Lead | Civil society and labour organisations; Indigenous peoples' organisations; Conservation science bodies; Regional and local governments | P0-03 | Consultation report, including the proxy hearings. | Not started |
| P0-08 | Finalise the requirements | Phase 0 | Design authority | Update the User Requirements Document and Solution Requirements Document from the consultation and the options appraisal, and complete the traceability between them. | Jan 2028 | Apr 2028 | 4 | Medium | Design Authority Lead | PMO Lead; Economic Security Lead; Basic Services Lead; Automation and AI Governance Lead; Purpose, Learning and Participation Lead; Planetary Stewardship Lead; Engagement and Legitimacy Lead; Legal and Policy Lead | P0-06, P0-07 | User Requirements Document v1.0 and Solution Requirements Document v1.0. | Not started |
| P0-09 | Set out the legal and treaty pathway | Phase 0 | Legal and policy | Analyse the legal routes: an international transition compact, national legislation and rights instruments. | Oct 2027 | Apr 2028 | 7 | Medium | Legal and Policy Lead | UN bodies; Academia and research institutes | P0-06 | Legal pathway paper and outline of the compact. | Not started |
| P0-10 | Outline the financing strategy | Phase 0 | Economic security | Set out how each phase could be financed, with relative sizing. Full costing follows in the Phase 1 business case. | Jan 2028 | May 2028 | 5 | Medium | Economic Security Lead | International financial institutions; Central banks | P0-05, P0-06 | Financing strategy outline. | Not started |
| P0-11 | Baseline the plan, RAIDD and benefits map | Phase 0 | Programme management | Bring the workstream plans together and baseline the Plan, RAIDD, RACI and benefits map for Phase 1. | Mar 2028 | May 2028 | 3 | Medium | Programme Director | PMO Lead; Benefits and Assurance Lead | P0-08, P0-09, P0-10 | Plan v1.0, RAIDD v1.0 and benefits map. | Not started |
| P0-12 | Run the independent assurance review | Phase 0 | Benefits and assurance | Review the final plan independently against the quality criteria in the PID. | May 2028 | Jun 2028 | 2 | Small | Benefits and Assurance Lead | Academia and research institutes | P0-11 | Assurance report with recommendations. | Not started |
| P0-13 | Approve the final plan and the Phase 1 mandate | Phase 0 | Programme management | The Programme Board approves the final plan and authorises Phase 1. | Jun 2028 | Jun 2028 | 1 | Small | Sponsor | Programme Board; Programme Director | P0-12 | Approved final plan and Phase 1 mandate. | Not started |
| P1-01 | Agree the international transition compact and set up its secretariat | Phase 1 | Legal and policy | Negotiate a compact among adopting states and establish a secretariat to support it. | Jul 2028 | Dec 2030 | 30 | Very large | Legal and Policy Lead | UN bodies; National governments | P0-13 | Compact open for signature and secretariat operating. | Not started |
| P1-02 | Set up the global automation observatory | Phase 1 | Automation and AI governance | Measure task automation, productivity, displacement and the distribution of gains by sector and country, and publish the results every year. | Jul 2028 | Dec 2029 | 18 | Large | Automation and AI Governance Lead | UN bodies; Academia and research institutes | P0-13 | Observatory publishing annual data. | Not started |
| P1-03 | Build the automation safety and accountability regime | Phase 1 | Automation and AI governance | Agree standards, certification, liability and redress for automated systems that affect the public. | Jan 2029 | Dec 2032 | 48 | Very large | Automation and AI Governance Lead | UN bodies; National governments; Industry | P1-01 | Standards, certification scheme and redress route. | Not started |
| P1-04 | Run basic income pilots at scale | Phase 1 | Economic security | Run regional and national income floor pilots in high-, middle- and low-income economies, each independently evaluated. | Jan 2029 | Dec 2032 | 48 | Very large | Economic Security Lead | National governments; Regional and local governments; Academia and research institutes | P0-10, P1-02 | Evaluated pilots in each income group of countries. | Not started |
| P1-05 | Design the automation dividend and public wealth funds | Phase 1 | Economic security | Design how returns from automated capital are shared, including public and shared ownership models. | Jan 2029 | Dec 2031 | 36 | Large | Economic Security Lead | Central banks; International financial institutions; National governments | P0-10 | Dividend mechanism and fund governance design. | Not started |
| P1-06 | Pilot universal basic services | Phase 1 | Basic services | Pilot universal provision of health, food, water, energy, transport and digital access. | Jan 2029 | Dec 2032 | 48 | Very large | Basic Services Lead | National governments; Regional and local governments | P0-13 | Evaluated service pilots. | Not started |
| P1-07 | Pilot homes for everyone | Phase 1 | Basic services | Use land reform, automated construction and retrofit to house everyone in the pilot regions. | Jan 2029 | Dec 2032 | 48 | Very large | Basic Services Lead | Regional and local governments; National governments; Industry | P0-13 | Evaluated housing pilots. | Not started |
| P1-08 | Pilot learning, purpose and contribution schemes | Phase 1 | Purpose, learning and participation | Pilot lifelong learning entitlements and ways to recognise care, civic, creative and scientific contribution. | Jan 2029 | Dec 2032 | 48 | Large | Purpose, Learning and Participation Lead | National governments; Regional and local governments; Civil society and labour organisations; Academia and research institutes | P0-13 | Evaluated pilots. | Not started |
| P1-09 | Baseline nature and set up the proxy panels | Phase 1 | Planetary stewardship | Support delivery of the 30 per cent protection target, baseline the condition of ecosystems and set up standing proxy panels for non-human users. | Jul 2028 | Dec 2030 | 30 | Large | Planetary Stewardship Lead | Conservation science bodies; UN bodies; Indigenous peoples' organisations | P0-13 | Ecosystem baseline and proxy panels in operation. | Not started |
| P1-10 | Set up the just transition finance facility | Phase 1 | Economic security | Set up a facility, mostly grant-funded, so that low- and middle-income countries can join the pilots and build delivery capacity. | Jan 2029 | Dec 2032 | 48 | Large | Economic Security Lead | International financial institutions; Central banks; UN bodies | P1-05 | Facility operating and funding pilots. | Not started |
| P1-11 | Design and pilot digital public infrastructure | Phase 1 | Design authority | Produce a reference design for identity, payment and data systems with privacy by design and non-digital alternatives, and pilot it. | Jan 2029 | Dec 2031 | 36 | Large | Design Authority Lead | National governments; Industry; Central banks | P0-13 | Reference design and pilot results. | Not started |
| P1-12 | Evaluate Phase 1 and hold the scale-up gate | Phase 1 | Benefits and assurance | Evaluate the pilots against the benefits and requirements, and advise the Programme Board on whether to start Phase 2. | Jul 2032 | Dec 2032 | 6 | Medium | Benefits and Assurance Lead | Academia and research institutes; PMO Lead | P1-04, P1-06, P1-07, P1-08 | Evaluation report and gate decision. | Not started |
| P2-01 | Legislate national income floors | Phase 2 | Economic security | Adopting countries legislate an unconditional income floor, or a mix of cash and services. | Jan 2033 | Dec 2037 | 60 | Very large | National governments | Economic Security Lead; Central banks; Regional and local governments | P1-12 | Income floors in law in adopting countries. | Not started |
| P2-02 | Scale the automation dividend | Phase 2 | Economic security | Build up public wealth funds from the automation dividend so that income floors are funded sustainably. | Jan 2033 | Dec 2040 | 96 | Very large | National governments | Economic Security Lead; Central banks; International financial institutions; Industry | P1-05, P1-12 | Public wealth funds paying for income floors. | Not started |
| P2-03 | Scale universal basic services | Phase 2 | Basic services | Roll out nationally the universal services proven in Phase 1. | Jan 2033 | Dec 2040 | 96 | Very large | National governments | Basic Services Lead; Regional and local governments; Industry | P1-12 | Universal services in adopting countries. | Not started |
| P2-04 | Deliver homes for everyone at scale | Phase 2 | Basic services | Provide an adequate, secure home for every person in adopting countries. | Jan 2033 | Dec 2040 | 96 | Very large | Regional and local governments | Basic Services Lead; National governments; Industry; International financial institutions | P1-07, P1-12 | Everyone adequately housed in adopting countries. | Not started |
| P2-05 | Provide global income support to the lowest-income countries | Phase 2 | Economic security | Make international transfers from the automation dividend so that income floors are not limited to rich countries. | Jan 2034 | Dec 2040 | 84 | Very large | International financial institutions | Economic Security Lead; UN bodies; Central banks | P1-10, P2-02 | Transfers funding income floors in the lowest-income countries. | Not started |
| P2-06 | Reform tax and public finance | Phase 2 | Economic security | Move the tax base from wages towards automated production, land values and resource rents. | Jan 2033 | Dec 2038 | 72 | Large | National governments | Economic Security Lead; International financial institutions | P1-05 | Reformed tax base in adopting countries. | Not started |
| P2-07 | Redesign education for purpose | Phase 2 | Purpose, learning and participation | Redesign education from preparation for employment to lifelong learning and contribution. | Jan 2034 | Dec 2040 | 84 | Large | National governments | Purpose, Learning and Participation Lead; Regional and local governments; Academia and research institutes | P1-08 | New education frameworks in adopting countries. | Not started |
| P2-08 | Restore ecosystems at scale | Phase 2 | Planetary stewardship | Use automation for rewilding, reforestation and the recovery of soils and oceans, overseen by the proxy panels. | Jan 2033 | Dec 2040 | 96 | Very large | UN bodies | Planetary Stewardship Lead; National governments; Conservation science bodies; Indigenous peoples' organisations; Industry | P1-09 | Restoration programmes meeting their targets. | Not started |
| P2-09 | Certify safe autonomy for critical services | Phase 2 | Automation and AI governance | Public oversight bodies certify the autonomous operation of critical services. | Jan 2033 | Dec 2038 | 72 | Large | UN bodies | Automation and AI Governance Lead; National governments; Industry | P1-03 | Certified critical services. | Not started |
| P2-10 | Hold the mid-programme review and refresh the plan | Phase 2 | Benefits and assurance | Review benefits, risks and the pace of automation, and refresh the plan for Phase 3. | Jan 2040 | Dec 2040 | 12 | Medium | Benefits and Assurance Lead | PMO Lead; Academia and research institutes | P2-01, P2-03, P2-04 | Review report and refreshed plan. | Not started |
| P3-01 | Raise income floors to sufficiency | Phase 3 | Economic security | Raise income floors in step with the share of production that is automated, until income from employment is optional. | Jan 2041 | Dec 2055 | 180 | Very large | National governments | Economic Security Lead; Central banks; International financial institutions | P2-10 | Income floors sufficient to live on without employment. | Not started |
| P3-02 | Separate livelihood from employment | Phase 3 | Legal and policy | Reform the pensions, benefits, contracts and taxes that assume paid work. | Jan 2041 | Dec 2050 | 120 | Very large | National governments | Legal and Policy Lead; Regional and local governments; Industry | P2-10 | Reformed entitlements and law in adopting countries. | Not started |
| P3-03 | Provide automated essentials at near-zero cost | Phase 3 | Basic services | Give everyone access to automated food, energy and transport at near-zero marginal cost. | Jan 2041 | Dec 2055 | 180 | Very large | National governments | Basic Services Lead; Industry; Regional and local governments | P2-03 | Essentials available to all at near-zero cost. | Not started |
| P3-04 | Bring living standards together across countries | Phase 3 | Economic security | Close the gap in income floors and services between countries. | Jan 2041 | Dec 2055 | 180 | Very large | UN bodies | Economic Security Lead; International financial institutions; National governments | P2-05 | Comparable floors and services in all adopting countries. | Not started |
| P3-05 | Return within planetary boundaries | Phase 3 | Planetary stewardship | Bring every planetary boundary back within its safe limit. | Jan 2041 | Dec 2055 | 180 | Very large | UN bodies | Planetary Stewardship Lead; National governments; Industry; Conservation science bodies | P2-08 | All planetary boundaries within safe limits. | Not started |
| P3-06 | Build local participation and purpose institutions | Phase 3 | Purpose, learning and participation | Establish permanent citizens' assemblies, commons, and care and cultural institutions at local level. | Jan 2041 | Dec 2055 | 180 | Large | Regional and local governments | Purpose, Learning and Participation Lead; Engagement and Legitimacy Lead; Civil society and labour organisations; National governments | P2-07 | Permanent local institutions in place. | Not started |
| P4-01 | Establish permanent stewardship institutions | Phase 4 | Legal and policy | Put in place standing institutions and a periodic review of the compact, with proxy representation for non-human users. | Jan 2056 | Ongoing | Ongoing | Large | UN bodies | Legal and Policy Lead; National governments; Civil society and labour organisations; Indigenous peoples' organisations; Conservation science bodies | P3-01, P3-05 | Standing institutions and review cycle. | Not started |
| P4-02 | Close the programme and hand over | Phase 4 | Programme management | Close the programme and hand its remaining responsibilities to the permanent institutions. | Jan 2056 | Dec 2057 | 24 | Medium | Sponsor | Programme Director; PMO Lead; Benefits and Assurance Lead | P4-01 | Closure report and handover. | Not started |
| X-01 | Control and report on the programme | Cross-cutting | Programme management | Integrated planning, progress reporting and review of the RAIDD throughout the programme. | Jan 2027 | Dec 2057 | 372 | Large | Programme Director | PMO Lead | P0-01 | Highlight reports, phase-end reports and a current plan. | Not started |
| X-02 | Track benefits and assure the programme | Cross-cutting | Benefits and assurance | Track benefits and run phase-gate and independent reviews. | Jan 2027 | Dec 2057 | 372 | Large | Benefits and Assurance Lead | Academia and research institutes; PMO Lead | P0-01 | Benefits reports and assurance reports. | Not started |
| X-03 | Engage the public and communicate | Cross-cutting | Engagement and legitimacy | Continuous engagement, transparency and feedback, including reports from the proxies for non-human users. | Jun 2027 | Dec 2057 | 367 | Large | Engagement and Legitimacy Lead | Civil society and labour organisations; Regional and local governments; Conservation science bodies | P0-03 | Public updates, open data and consultation records. | Not started |
| X-04 | Keep rights and law aligned | Cross-cutting | Legal and policy | Keep rights instruments, treaties and national law aligned with the plan. | Jan 2028 | Dec 2057 | 360 | Medium | Legal and Policy Lead | UN bodies; National governments | P0-09 | Legal alignment reviews. | Not started |
| X-05 | Run programme support and document control | Cross-cutting | Programme management | Maintain the RAIDD log, document versions and the Control register. | Jan 2027 | Dec 2057 | 372 | Medium | PMO Lead | PMO Lead | P0-01 | Current RAIDD log and Control register. | Not started |
Timeline
v0.1 draft | 10 November 2026
Post Automation Utopia programme | Owner: Programme Director
One column per year. A filled cell means the step is active in that year. The bars follow the Start and End dates on the Plan tab.
| ID | Step | Phase | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 | 2035 | 2036 | 2037 | 2038 | 2039 | 2040 | 2041 | 2042 | 2043 | 2044 | 2045 | 2046 | 2047 | 2048 | 2049 | 2050 | 2051 | 2052 | 2053 | 2054 | 2055 | 2056 | 2057 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P0-01 | Mobilise the programme | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-02 | Agree governance and decision rights | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-03 | Map stakeholders and agree the engagement strategy | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-04 | Review the evidence | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-05 | Model scenarios and fiscal options | Phase 0 | ■ | ■ | |||||||||||||||||||||||||||||
| P0-06 | Appraise the options for each pillar | Phase 0 | ■ | ■ | |||||||||||||||||||||||||||||
| P0-07 | Consult worldwide | Phase 0 | ■ | ■ | |||||||||||||||||||||||||||||
| P0-08 | Finalise the requirements | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-09 | Set out the legal and treaty pathway | Phase 0 | ■ | ■ | |||||||||||||||||||||||||||||
| P0-10 | Outline the financing strategy | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-11 | Baseline the plan, RAIDD and benefits map | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-12 | Run the independent assurance review | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P0-13 | Approve the final plan and the Phase 1 mandate | Phase 0 | ■ | ||||||||||||||||||||||||||||||
| P1-01 | Agree the international transition compact and set up its secretariat | Phase 1 | ■ | ■ | ■ | ||||||||||||||||||||||||||||
| P1-02 | Set up the global automation observatory | Phase 1 | ■ | ■ | |||||||||||||||||||||||||||||
| P1-03 | Build the automation safety and accountability regime | Phase 1 | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||||
| P1-04 | Run basic income pilots at scale | Phase 1 | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||||
| P1-05 | Design the automation dividend and public wealth funds | Phase 1 | ■ | ■ | ■ | ||||||||||||||||||||||||||||
| P1-06 | Pilot universal basic services | Phase 1 | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||||
| P1-07 | Pilot homes for everyone | Phase 1 | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||||
| P1-08 | Pilot learning, purpose and contribution schemes | Phase 1 | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||||
| P1-09 | Baseline nature and set up the proxy panels | Phase 1 | ■ | ■ | ■ | ||||||||||||||||||||||||||||
| P1-10 | Set up the just transition finance facility | Phase 1 | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||||
| P1-11 | Design and pilot digital public infrastructure | Phase 1 | ■ | ■ | ■ | ||||||||||||||||||||||||||||
| P1-12 | Evaluate Phase 1 and hold the scale-up gate | Phase 1 | ■ | ||||||||||||||||||||||||||||||
| P2-01 | Legislate national income floors | Phase 2 | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||||||||||||
| P2-02 | Scale the automation dividend | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||||
| P2-03 | Scale universal basic services | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||||
| P2-04 | Deliver homes for everyone at scale | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||||
| P2-05 | Provide global income support to the lowest-income countries | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||||||||||
| P2-06 | Reform tax and public finance | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||
| P2-07 | Redesign education for purpose | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||||||||||
| P2-08 | Restore ecosystems at scale | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||||
| P2-09 | Certify safe autonomy for critical services | Phase 2 | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||||||
| P2-10 | Hold the mid-programme review and refresh the plan | Phase 2 | ■ | ||||||||||||||||||||||||||||||
| P3-01 | Raise income floors to sufficiency | Phase 3 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||
| P3-02 | Separate livelihood from employment | Phase 3 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | |||||||||||||||||||||
| P3-03 | Provide automated essentials at near-zero cost | Phase 3 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||
| P3-04 | Bring living standards together across countries | Phase 3 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||
| P3-05 | Return within planetary boundaries | Phase 3 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||
| P3-06 | Build local participation and purpose institutions | Phase 3 | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ||||||||||||||||
| P4-01 | Establish permanent stewardship institutions | Phase 4 | ■ | ■ | |||||||||||||||||||||||||||||
| P4-02 | Close the programme and hand over | Phase 4 | ■ | ■ | |||||||||||||||||||||||||||||
| X-01 | Control and report on the programme | Cross-cutting | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ |
| X-02 | Track benefits and assure the programme | Cross-cutting | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ |
| X-03 | Engage the public and communicate | Cross-cutting | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ |
| X-04 | Keep rights and law aligned | Cross-cutting | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | |
| X-05 | Run programme support and document control | Cross-cutting | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ | ■ |
Phases
Post Automation Utopia programme | v0.1 draft | 10 November 2026 | Owner: Programme Director
Phase dates are recommendations for planning. Later phases move with the pace of automation measured by the observatory.
| Phase | Name | Start | End | Aim | Steps in the plan |
|---|---|---|---|---|---|
| Phase 0 | Finalise the plan | Jan 2027 | Jun 2028 | Take the v0.1 draft to an approved final plan with a mandate for Phase 1. | 13 |
| Phase 1 | Foundations and pilots | Jul 2028 | Dec 2032 | Set up the institutions, measurement and safety regime, and pilot every pillar at scale in a range of countries. | 12 |
| Phase 2 | Scale national floors | Jan 2033 | Dec 2040 | Legislate and scale income floors, basic services and housing, fund them from the automation dividend, and restore nature at scale. | 10 |
| Phase 3 | Transition at scale | Jan 2041 | Dec 2055 | Raise floors to sufficiency as automation approaches full coverage, separate livelihood from employment, and bring living standards together across countries. | 6 |
| Phase 4 | Stewardship | Jan 2056 | Ongoing | Hand over to permanent stewardship institutions and close the programme. | 2 |
| Cross-cutting | Runs through every phase | Jan 2027 | Dec 2057 | Control, assurance, engagement, legal alignment and programme support that continue throughout. | 5 |
| All steps | 48 |
Key
Post Automation Utopia programme | v0.1 draft | 10 November 2026 | Owner: Programme Director
How to read the Plan tab.
Effort sizes
| Size | Meaning | Code |
|---|---|---|
| Small | A few months for a small core team, with little external input. | S |
| Medium | Several months for one workstream, with targeted external input. | M |
| Large | One to two years, or longer at low intensity, involving several workstreams and delivery institutions. | L |
| Very large | Multi-year delivery in many countries, involving many institutions. | XL |
| Effort is sized relatively. Nothing in the plan has been costed. |
Status values
| Status | Meaning |
|---|---|
| Not started | Work has not begun. |
| In progress | Work is under way. |
| Complete | The output has been delivered and accepted. |
| On hold | Work has stopped until a decision is taken. |
Columns on the Plan tab
| Column | What it holds |
|---|---|
| ID | Step reference. P0 to P4 are the phases. X marks cross-cutting steps that run through every phase. |
| Step | The step. Steps P0-01 to P0-13 are the Next steps (NS-01 to NS-13). |
| Phase | The phase the step belongs to. The Phases tab lists the phases and their dates. |
| Workstream | The workstream that leads the step. |
| Description | What the step does. |
| Start and End | First and last month of the step. They are recommendations for planning, not forecasts. |
| Duration (months) | Calculated from Start and End, counting both months. |
| Effort | Relative size of the work. See Effort sizes above. |
| Owner (accountable) | The one role accountable for the step. It is the A in the RACI. |
| Delivered by (responsible) | The roles that do the work. They are the R in the RACI. |
| Depends on | Steps whose outputs this step needs. |
| Output | What the step produces. |
| Status | One of the status values above. |